实拍进度真快!光谷这个延期项目要交付了!
近日,据网友最新实拍绿地光谷星河绘项目最新进展,并表示绿地光谷星河绘即将交付!从网友分享的图和此前3、4月份的项目实拍图对比,建设进度真的好快啊!
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/570fcd098f514dcb893fa5e001be12ad~tplv-tt-large.image?x-expires=2000154032&x-signature=yOkoGJhTMxd0hqIrq7mz32hVj9U%3D
据了解,该项目备案为毛坯交付,合同约定交付时间为2022年12月31日,目前拟于2023年6月30日交付。按前期施工计划,该项目部分楼栋可达到交付条件。应业主要求,结合现场实际情况,对该项目部分达到交付条件楼栋,开发建设单位拟定2023年6月30日前计分别三批举行交付。
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/e7ad07ce1f8e4b3295279044259eab42~tplv-tt-large.image?x-expires=2000154032&x-signature=q10aJ6y04funFJtYjklmwBFIJm0%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/7e5bfa7a128249c3b99588755973a809~tplv-tt-large.image?x-expires=2000154032&x-signature=yKKkT%2BlIVIuzZUEh4RzhiRmj%2BTg%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/3e108b8b369748bb92b63b267b5f6f1e~tplv-tt-large.image?x-expires=2000154032&x-signature=NfyLNBQYtEOKi8E23%2Bd4ntyfEKE%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/b9c38fe1ece24853bbe98eb28a1b8a0d~tplv-tt-large.image?x-expires=2000154032&x-signature=vPYApOR%2Bic9PlJL28AZJP9%2Fnr38%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/c33470a976214660a7d0abf4237d6cde~tplv-tt-large.image?x-expires=2000154032&x-signature=hv1bYoN8dvVWC0Os8%2BA1yUPeD%2Bo%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/147fc4171c92413aa38990aa47038515~tplv-tt-large.image?x-expires=2000154032&x-signature=8ttvP1FP3rCpdZt5XqCe1ImIuGk%3D
不久前,4月23日,绿地发布光谷星河绘项目工程进度:
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/c47fbcdebfb54fb3bc2eecbd088de155~tplv-tt-large.image?x-expires=2000154032&x-signature=d48doZk7xmqFGez1WVpDsqnacdc%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/4976c531168d4a37921f9eed222b1e7b~tplv-tt-large.image?x-expires=2000153819&x-signature=iJC7Bae63JKttJLJ2YWr6w%2B6l3E%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/f6a7a79f856348d1b225652d6b496fba~tplv-tt-large.image?x-expires=2000154032&x-signature=%2BcIg2%2BPDSjNzGmhtmMx0%2B1WY16s%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/273e66dbd7a64bdfb202e515d464ae43~tplv-tt-large.image?x-expires=2000154033&x-signature=3DtvfgoO4tHKfO1rPtY%2FDYWPfk4%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/2b4f88fb344349d29b12aa49c66184a5~tplv-tt-large.image?x-expires=2000154033&x-signature=H8e7EZSICgAduWKmnhkcfyvv8%2FQ%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/61f191580dc1442eb38e46826c92704a~tplv-tt-large.image?x-expires=2000154033&x-signature=F8TDeidDLHclpB0ap1fjjDIrclw%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/f2d9b014417042e0b7a562690c40d8c1~tplv-tt-large.image?x-expires=2000154033&x-signature=R0S0Z%2FLx5gWNMZYn98B4ou0Q9mY%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/11e1f57ab4cd4ba7933d6aefac89f835~tplv-tt-large.image?x-expires=2000154033&x-signature=SjdhAj9E4WNPMdT%2F5WQfzaInEyg%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/76ec85205c204e1fb3aacfc0936398b9~tplv-tt-large.image?x-expires=2000154033&x-signature=NrIgbvOkUrdYOzfmPG1SO0lrBO0%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/62f79099e6e84349a27f69ad17d6e6ea~tplv-tt-large.image?x-expires=2000154033&x-signature=vkIK8ey0koPs%2FqR%2FjGNnntSP93w%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/e6bd34aa224647f1bb6aa12d0a86a0af~tplv-tt-large.image?x-expires=2000154033&x-signature=q9saJErA1e5nWYif73qWkDppTLM%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/1f61bd89d39446b18c8b66882404ddb1~tplv-tt-large.image?x-expires=2000154033&x-signature=RiHjKLnp8fB5MKtwKcGApnl5Qbg%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/321e77e9fa334710a3d4fc336df97c3e~tplv-tt-large.image?x-expires=2000154033&x-signature=ZsLeezeLovxF%2BjQdG52Cf8%2FrkZk%3D
此前,绿地光谷星河绘2023.03.23工程进度:
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/b10ba399f78b4c68924331f86944da37~tplv-tt-large.image?x-expires=2000154033&x-signature=vwTD0iJfhuA%2FHXU40cdieLrDMs0%3D
这是A1.A2栋整个外立面,外墙还没做好
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/9bb5df6772ee4ee58c24eeecb326f184~tplv-tt-large.image?x-expires=2000154033&x-signature=m8zwTK0qUdoZxaB%2BwMeBFz1AAxE%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/8a99bfc1f16c4ac092d46f39fc9e94d9~tplv-tt-large.image?x-expires=2000154033&x-signature=octNW0b%2FMwZWN8yHMyspckEICps%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/3c09adab5cd5486c9838f668c361463c~tplv-tt-large.image?x-expires=2000154033&x-signature=loCU2BYO7uuEfmHD75MdHHZ8D%2BY%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/259d947361394d98b5a075dfac5f0799~tplv-tt-large.image?x-expires=2000154033&x-signature=2tS0AQ%2BGqywATHQIw16Vn1h5eBU%3D
这是A3栋
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/14b17b30b00e4440b83ffb6e04132124~tplv-tt-large.image?x-expires=2000154033&x-signature=GU6T7rNgVS2DFg1tJ1OIkAhQuYA%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/71a47d19914e4049b1ece3635e4c0f01~tplv-tt-large.image?x-expires=2000154033&x-signature=IADUss0xVrxlPvbwOSOheTF3O6I%3D
这是A5栋
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/a84dd799b4e14dd7be6c02e32457aac8~tplv-tt-large.image?x-expires=2000154033&x-signature=7nfXa1EDphor31RVqPbydYoRAms%3D
这是A6、A7栋
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/c3fe9b13c8cf4aa7b7e2e4991ada18f9~tplv-tt-large.image?x-expires=2000154033&x-signature=AKOwvHjrCZIRIMnixnsgI8dHm%2Bg%3D
这是A6栋
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/cd3911daa8a44c699fdbafa927b51daf~tplv-tt-large.image?x-expires=2000154033&x-signature=d%2BXeM4%2FF77oOr1K2E1QdlT8eMdY%3D
A7整体
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/f0dd2d352fc546da8effb5891dafce95~tplv-tt-large.image?x-expires=2000154033&x-signature=Bp6iz6cxwTDthFbO2G1X8vW0GIM%3D
这是A9栋
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/a6006195f4cd48cda22a7a2cf32cf3e9~tplv-tt-large.image?x-expires=2000154033&x-signature=1zXP9r93gUdxiu%2Bv7H%2BQ7AnjqQU%3D
这个是A11
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/dc89381205bb4c0091ae9a2f880b14ac~tplv-tt-large.image?x-expires=2000154033&x-signature=zZVL2W210y7wMSBNdzLNGSpu3g8%3D
据此前官方回复:经查,绿地星河绘项目备案为毛坯交付,合同约定交付时间为2022年12月31日,目前拟于2023年6月30日交付。按前期施工计划,该项目部分楼栋可达到交付条件。应业主要求,结合现场实际情况,对该项目部分达到交付条件楼栋,开发建设单位拟定2023年6月30日前计分别三批举行交付,于2023年6月30日完成整体交付,具体交付计划及时间以企业最终通知为准。按照每月见面会和施工进度公示工作机制,专班已督促建设单位制定了详细的施工计划,并定期向业主通报项目进度,协调企业通过工地开放日、定期会商会等形式,让业主及时了解项目进度,并做好业主反映问题收集整改。2月10日和2月14日建设单位分别将该项目A、B区楼栋完工计划表发至业主群举行公布。截至目前,该项目所有楼栋主体结构已全部封顶,相关配套工程均已进场施工,供电配套工程预计本月进场施工,进入项目后期建设重要阶段,确保项目顺利交付。同时根据每月施工资金需求,工作专班按期分批拨付“保交楼”资金,项目现场施工正常。后续,围绕“三保”目标,根据“一楼一策”、“一企一策”督导企业切实承担主体责任,同时,加强现场巡查,把握项目建设进度,督促项目竣工交付。
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/0b243e7b2fb84ec6b8d00a47864fb9cc~tplv-tt-large.image?x-expires=2000154033&x-signature=0rH%2B%2Fhj%2BpRen6s4gqrd2Ufm1ABQ%3D
https://p3-sign.toutiaoimg.com/tos-cn-i-qvj2lq49k0/c441f7f5ab0e404b998f543b0e4dcf2f~tplv-tt-large.image?x-expires=2000154033&x-signature=IkHJVz8tqXG%2BTBvIEkyQ4V3EQYo%3D
落位图
(来源:光谷城事)
免责声明:如果侵犯了您的权益,请联系光谷社区站长,我们会及时删除侵权内容,谢谢合作! 怎么不放现在a区的照片,放的都是b区照片,你去看看3.23到现在a区的进度对比,还好意思说出进度真快这种话吗,按这个进度星河绘A区06.30能交房就见鬼了,明显的保b弃a,a区成弃子,这就是所谓的保交楼